PRESENT
Chris Fonseca Authority Member
James Dickie Supervisor, Procurement and Contract Management
Aaron D'Souza Project Coordinator, PMO
Judith Reda Executive Assistant, CEO and Chair's Office
Rocco Sgambelluri Chief Financial Officer
Albert Thomas Contract Coordinator, Procurement and Contract Management
Jordan Budway Administrative Assistant, Construction Services
Craig Losos Restoration and Environmental Monitoring Projects, Technologist
Thomas Sciscione Restoration Services, Technologist
1. TENDER OPENING COMMITTEE
1.1 MEADOWCLIFFE DRIVE STABILIZATION PROJECT
Supply and Delivery of Cobble Stones
RSD 13-017
BIDDER Total Value of Tender Deposit 10% Addendum
Contract (Bid Bond or (Acknowledge)
(Plus HST) Certified Cheque)
Allstone Quarry Products Inc. No Bid n/a n/a
Bot Aggregates Limited No Bid n/a n/a
Brent Quarries No Bid n/a n/a
B-Town Group No Bid n/a n/a
CMB (St. Mary Cement) No Bid n/a n/a
Dufferin Aggregates $113,560.00 Yes Yes
Earthco Soils Mixtures No Bid n/a n/a
Fowler Construction $128,960.00 Yes Yes
Glenn Windrem $139,800.00 Yes Yes
Greenwood Construction No Bid n/a n/a
J.C. Rock Limited No Bid n/a n/a
1
MEADOWCLIFFE DRIVE STABILIZATION PROJECT (Cont'd)
BIDDER Total Value of Tender Deposit 10% Addendum
Contract (Bid Bond or (Acknowledge)
(Plus HST) Certified Cheque)
James Dick Construction $162,200.00 Yes Yes
Lafarge Aggregates No Bid n/a n/a
Miller Group No Bid n/a n/a
Nelson Aggregate Co. $103,600.00 Yes Yes
R.W. Tomlinson Ltd. No Bid n/a n/a
Strada Aggregates No Bid n/a n/a
TBG Landscape Inc. $140,000.00 Yes Yes
Tomlinson Group No Bid n/a n/a
Young's Aggregate No Bid n/a n/a
Rock Valley $175,520.00 Yes Yes
Brock Aggregates $170,760.00 Yes Yes
'Cambridge Aggregates Services $122,000.00 Yes No '
Inc.
IDale 0 Hewell Construction $140,000.00 Yes Yes
1.2 HUMBER STATION ROAD MUNICIPAL EA PROJECT
PMO13-02, Request for Proposal (RFP)
BIDDER Basic Fee Permitted Total Value of Addendums
(Plus HST) Expenses Contract Acknowledged
(Plus HST) (Plus HST)
iAquafor Beech $60.520.00 $6,150.00 $66,670.00 Yes
ICole Engineering $34,941.00 $4,890.00 $39,831.00 Yes
IGHD $43,015.00 $600.00 $43,615.00 Yes
'Limited and Associates $38,090.00 $5,490.00 $43,580.00 Yes
Limited
BURS Corporation $48,022.41 $1,475.00 $49,497.41 Yes
(Walter Fedy $35,590.00 $3,950.00 $39,540.00 Yes
IT WAS AGREED AND RECOMMENDED THAT the tender received as listed above be referred
to staff for review.
/j r
2
Toronto and Region
7.1001Conservation
Authority
MEETING OF THE TENDER OPENING COMMITTEE #2/13
March 1, 2013
The Tender Opening Committee Meeting #2/13, was held in Weston Room B, Black
Creek Pioneer Village, on Friday, March 1, 2013. The Chair Maria Augimeri, called the
meeting to order at 9:18 a.m.
PRESENT
Maria Augimeri Vice Chair, Authority
James Dickie Supervisor, Procurement and Contract Management
Bill Jewell Supervisor, Maintenance
Nick Saccone Director, Restoration Services
Kathy Stranks Manager, Corporate Secretariat
1. TENDER OPENING COMMITTEE
1.1 FRENCHMAN'S BAY CHANNEL DREDGING
RSD13-21
BIDDER Total Tender Addendum Tender
Amount Acknowledgement Deposit 10%
(Plus HST) (Bid Bond or
Certified
Cheque)
(Catalina Excavating $188,850.00 Yes Yes
(Dean Construction Co. Ltd. $303,300.00 No Yes
lElirpa Construction No Bid n/a n/a
IGalcon Marine $152,860.00 Yes Yes
McPherson-Andrews Contracting No Bid n/a n/a
Limited
Metric Contracting Services Co. $329,000.00 Yes Yes
Newalta $334,480.00 No Yes
Ontario Construction Company Ltd. $180,925.00 Yes Yes
Richardson Workboats No Bid n/a n/a
Sumerville Construction No Bid n/a n/a
Titan Contracting Inc. No Bid n/a n/a
3
1.2 MID-SIZE TRUCK
FM2013-2
BIDDER Total Tender Addeddum
Amount Acknowledgement
(Plus HST)
Woodbine Truck Centre Ltd. $113,728.00 Yes
Thorncrest Sherway Inc. $105,629.00 Yes
Tallman Truck Centre (Toronto) Limited $116,700.00 Yes
Scarborough Truck Centre No Bid n/a
Altruck International Truck Centre No Bid n/a
Kenworth Toronto Ltd. No Bid n/a
Kenworth Truck Centre No Bid n/a
Dixie Ford No Bid n/a
Kennedy Ford Sales No Bid n/a
IT WAS AGREED AND RECOMMENDED THAT the tender received as listed above be referred
to staff for review.
/ks
4
0)1114\1"4
Toronto and Region
sW Conservation
Authority
MEETING OF THE TENDER OPENING COMMITTEE #3/13
March 22, 2013
The Tender Opening Committee Meeting #3/13, was held in Weston Room B, Black
Creek Pioneer Village, on Friday, March 22, 2013. The Chair Gerri Lynn O'Connor, called
the meeting to order at 9:05 a.m.
PRESENT
Aaron D'Souza Project Coordinator, PMO
James Dickie Supervisor, Procurement and Contract Management
Craig Mitchell Supervisor, Flood Infrastructure
Lisa Moore Co-ordinator II, Flood Risk Management
Gerri Lynn O'Connor Chair
Natalie Racette Project Assistant, Restoration & Environmental Monitoring Projects
Rocco Sgambelluri Chief Financial Officer
John Stille Project Manager, Restoration and Environmental Monitoring
Kathy Stranks Manager, Corporate Secretariat
1. TENDER OPENING COMMITTEE
1.1 ALBION HILLS FIELD CENTRE PHASE 5 RETROFIT CLOSING
RFP PMO13-03
BIDDER Total Value of Contract Addendum(s) #1,2,3,4 & 5
(Plus HST) Acknowledged
Cool Earth Architecture Inc. $93,170.00 Yes
Michael Cicerani Architects $105,023.00 Yes
Montgomery Sisam Disqualified n/a
Paul Didur Architects $70,675.00 Yes
Ten 2 Four $44,140.00 Yes
+VG Architects $64,800.00 Yes
5
1.2 STOUFFVILLE DAM SAFETY REVIEW
RFP FMS13-01
BIDDER Total Tender Amount
(Plus HST)
IBI Group $89,995.95
KGS Group Consulting Engineers $134,344.00
AECOM $127,701.30
Sanchez Engineering Inc. $103,460.00
AMEC Environment & Infrastructure $77,240.00
Hatch Ltd. $90,596.00
Coffey Geotechnics $103,777.00
GHD $99,690.00
WESA $59,988.00
1.3 SUPPLY OF RENTAL RATES FOR AN OPERATED HYDRAULIC BACKHOE
RSD13-036 - Hydraulic Backhoe Crawler Mounted (16,300 kg)
BIDDER Rate Per Hour Addendum
(Plus HST) Acknowledged
Elirpa Construction & Materials Limited $110.00 No
Fisher Excavating and Grading $135.00 Yes
Sierra Excavating Enterprises Inc. $190.00 No
Valefield Contracting Inc. $89.00 No
The Landscape Gardener $85.00 Yes
TMi Contracting $75.00 No
CSL Group No Bid n/a
Sorbara Group No Bid n/a
Diamond Earthworks Corporation No Bid n/a
Impact Earthmoving Group No Bid n/a
IT WAS AGREED AND RECOMMENDED THAT the tender received as listed above be referred
to staff for review.
/ks
6
Toronto and Region
)111114\1"4em'0
Conservation
Authority
MEETING OF THE TENDER OPENING COMMITTEE #4/13
April 12, 2013
The Tender Opening Committee Meeting #4/13, was held in Weston Room B, Black
Creek Pioneer Village, on Friday, April 12, 2013. The Chair Gerri Lynn O'Connor, called
the meeting to order at 10:23 a.m.
PRESENT
James Dickie Supervisor, Procurement and Contract Management
Gerri Lynn O'Connor Chair
Rocco Sgambelluri Chief Financial Officer
Kathy Stranks Manager, Corporate Secretariat
1. TENDER OPENING COMMITTEE
1.1 MEADOWCLIFFE DRIVE SHORELINE IMPROVEMENT PROJECT
Supply & Delivery of 4-6 tonne Stackable Armour Stone
RSD13-037
BIDDERS Total Tender Addendum Tender Deposit 10%
Amount Acknowledged Bid Bond or
Certified Cheque
Nelson Aggregate Co. No Bid n/a n/a
Strada Aggregates $264,775 Yes Yes
Glenn Windrem Trucking $220,500 Yes Yes
C.D.R. Young's Aggregates Inc. $195,475 Yes Yes
Landvision Contracting $196,000 Yes Yes
B-Town Group $198,800 Yes Yes
IT WAS AGREED AND RECOMMENDED THAT the tender received as listed above be referred
to staff for review.
/ks
7
Toronto and Region
I;1001Conservation
Authority
MEETING OF THE TENDER OPENING COMMITTEE #5/13
April 26, 2013
The Tender Opening Committee Meeting #5/13, was held in Weston Room B, Black
Creek Pioneer Village, on Friday, April 26, 2013. The Chair Gerri Lynn O'Connor, called
the meeting to order at 8:45 a.m.
PRESENT
Jordan Budway Administrative Assistant, Construction Services
James Dickie Supervisor, Procurement and Contract Management
Chris Gerstenkorn Senior Manager, Information Services / Technology
Bill Jewell Supervisor, Maintenance
Danny Moro Project Manager, Restoration Services
Gerri Lynn O'Connor Chair
Rick Portiss Manager, Environmental Monitoring Projects
Rocco Sgambelluri Chief Financial Officer
Kathy Stranks Manager, Corporate Secretariat
1. TENDER OPENING COMMITTEE
1.1 CLAIREVILLE CONSERVATION AREA WATER MAIN PROJECT
Decommisssion & Installation of water main and Sewer Connection
RSD13-028
Total Tender Addendum Tender Deposit
Amoung Acknowledged 10%
BIDDERS (Plus HST) (BID BOND or
CERTIFIED
CHEQUE)
Develco Contracting $331,353.00 Yes Yes
Direct Underground Inc. $350,880.00 Yes Yes
Drainstar Contracting Ltd. $794,000.00 Yes Yes
Four Seasons Site $334,000.00 Yes Yes
Development
Kenwood Trenching & $496,900.00 Yes Yes
Excavating
TBG Landscape Inc. $227,677.50 Yes Yes
8
1.3 ALFRED KEUHNE BOULEVARD PROJECT
Sewer Encasement Works
RSD13-038
BIDDERS Total Tender Addendum Tender Deposit
Amount Acknowledged 10%
(Plus HST) (BID BOND or
CERTIFIED
CHEQUE)
Develco Contracting Inc. $55,500.00 Yes Yes
Drainstar Contracting Ltd $129,800.00 Yes Yes
Four Seasons Site Dev $39,500.00 Yes Yes
McPherson Andrews $66,934.00 Yes Yes
Serve Contruction $44,300.00 Yes Yes
TBG Landscape $66,460.00 Yes Yes
1.4 CABLE CONDUIT PROJECTS
Cable Conduit Installations
RSD13-039 to RSD13-052
Contract No. Alpeza General A.Vanegmond Avertex Utility Dilisado Four Seasons Langley R.Chad Trinity
Construction Construction Solutions Enterprise Site Utilities General Communication
(Plus HST) (Plus HST) (Plus HST) (Plus HST) (Plus HST) (Plus HST) Construction (Plus HST)
(Plus HST)
RSD13-039 $102,440 00 $272,854 00 $125,162 00 $102,380.00 $126,740.00 $91,310 00 $165,918 00 $114,706 82
RSD13-040 $18,426.00 $53,568 00 $23,446.00 $20,540.00 $27,040.00 $17,058 00 $31,878 00 $19,375.72
RSD13-041 $16,128 00 $45,583 00 $20,080 00 $17,990.00 $23,980.00 $14,406.00 $27,186.00 $16,258.96
RSD13-042 $31,024.00 $85,884 00 $38,058.00 $32,060 00 $44,040 00 $28,248 00 $51,028 00 $32,606 66
RSD13-043 $10,856 00 $33,348 00 $13,058 00 $12,220 00 $18,880 00 $9,196 00 $18,616.00 $9,550 11
RSD13-044 $4,716.00 $28,108.00 $7,118.00 $7,720 00 $13,480.00 $4,516 00 $10,336 00 $4,609.91
RSD13-045 $23,576 00 $137,866 00 $28,858 00 $24,640 00 $39,960 00 $21,322 00 $39,422 00 $23,881 32
RSD13-046 $9,864 00 $31,932.00 $12,002.00 $11,420 00 No Bid $8,364 00 $17,144 00 $8,572 55
RSD13-047 $26,454 00 $69,827 00 $29,584 00 $25,190 00 No Bid $21,894 00 $40,434 00 $24,553 56
RSD13-048 $5,336.00 $25,668.00 $7,778.00 $8,220 00 No Bid $5,036 00 $11,256.00 $5,214 67
RSD13-049 $44,876 00 $111,038 00 $49,634.00 $41,280 00 No Bid $37,046 00 $66,946 00 $43,527 51
RSD13-050 $38,580 00 $114,850 00 $42,414.00 $35,360 00 No Bid $31,680 00 $58,100 00 $36,640 11
RSD13-051 $25,524 00 $67,562 00 $28,594 00 $24,440 00 No Bid $21,114.00 $39,054.00 $23,636.81
RSD13-052 $9,182 00 $30,271 00 $11,276 00 $10,870 00 No Bid $7,792 00 $16,132 00 $7,914 23
'Addendum Yes Yes Yes Yes Yes Yes Yes Yes
Acknowledged
Tender Deposit Yes Yes Yes Yes Yes Yes Yes Yes
10%(Bid Bond
or Certified
Cheque)
9
1.5 MUD CREEK REACH 5 PROJECT
Supply & Delivery of 2-4 Tonne Stackable Armour Stone
RSD13-053
BIDDERS Total Tender Addendum Tender Deposit
Amount Acknowledged 10%
(Plus HST) (BID BOND or
CERTIFIED
CHEQUE)
Brock Aggregates No Bid n/a n/a
B-Town Group $82,049.50 Yes Yes
CDR Young $100,538.10 Yes Yes
Glenn Windrem $94,640.00 Yes Yes
James Dick Construction No Bid n/a n/a
JC Rock $92,105.00 Yes Yes
Miller Paving No Bid n/a n/a
Nelson Aggregate Co. No Bid n/a n/a
Strada Aggregates No Bid n/a n/a
TBG Landscape $89,570.00 Yes Yes
Natural Stone Source Ontario $76,050.00 Yes Yes
Limestone & Forestry Products $87,204.00 Yes Yes
The Newman Touch No Bid n/a n/a
IT WAS AGREED AND RECOMMENDED THAT the tender received as listed above be referred
to staff for review.
/ks
10
0)11114\1"4
Toronto and Region
sW Conservation
Authority
MEETING OF THE TENDER OPENING COMMITTEE #6/13
May 24, 2013
The Tender Opening Committee Meeting #6/13, was held in Weston Room B, Black
Creek Pioneer Village, on Friday, May 24, 2013. The Chair Gerri Lynn O'Connor, called
the meeting to order at 8:52 a.m.
PRESENT
Aaron D'Souza Project Coordinator, PMO
Lisa Moore Project Coordinator, PMO
Gerri Lynn O'Connor Chair, Authority
Rocco Sgambelluri Chief Financial Officer
Kathy Stranks Manager, Corporate Secretariat
1. TENDER OPENING COMMITTEE
1.1 SWAN LAKE RETROFIT AND RENOVATION PROJECT
Contractt PMO13-04
BIDDERS Total Value of Addendum(s) 10% Tender Deposit
Contract Addendum 1, 2 & 3 Bid Bond Only
(Plus HST)
Ameresco $2,500,000.00 Yes Yes
Berkim Construction Inc. $1,728,350.00 Yes Yes
P & C General Contracting No Bid n/a n/a
Pre-Eng Construction Ltd. $2,195,000.00 Yes Yes
Silver Birch Contracting Ltd. $1,890,000.00 Yes Yes
Steelcore Construction Ltd. $1,797,500.00 Yes Yes
Struct-Con Construction Ltd. $1,792,000.00 Yes Yes
Vema Corp $2,210,000.00 Yes Yes
W.S. Morgan Construction Ltd. No Bid n/a n/a
IT WAS AGREED AND RECOMMENDED THAT the tender received as listed above be referred
to staff for review.
/ks
11
0)111114\1"4
Toronto and Region
sW Conservation
Authority
MEETING OF THE TENDER OPENING COMMITTEE #7/13
June 7, 2013
The Tender Opening Committee Meeting #7/13, was held in the Flag Room, Mimico
Curising Club, on Friday, June 7, 2013. The Chair Gerri Lynn O'Connor, called the
meeting to order at 11:35 a.m.
PRESENT
James Dickie Supervisor, Procurement and Contract Management
Mark Preston Senior Supervisor, Construction Services
Gerri Lynn O'Connor Chair, Authority
Rocco Sgambelluri Chief Financial Officer
Kathy Stranks Manager, Corporate Secretariat
1. TENDER OPENING COMMITTEE
1.1 COATSWORTH CUT PROJECT - CHANNEL DREDGING WORKS
Contract RSD13-080
BIDDER Total Tender Addendum Tender Deposit 10%
Amount Acknowledgement (Bid Bond or
(Plus HST) Certified Cheque)
(Catalina Excavating $91,270.00 Yes Yes
(Dean Construction $236,499.00 Yes Yes
IGalcon Marine Ltd. $97,450.00 Yes Yes
(Metric No Bid n/a n/a
(Ontario Construction No Bid n/a n/a
12
1.2 SUPPLY & DELIVERY OF AGGREGATES
Bob Hunter Memorial Park, City of Markham
Supply & Delivery of approximately 7,500 tonnes of 19mm crusher run
Limeshone
Contract RSD13-085
BIDDER Total Contract Price Tender Security
(Plus HST)
Glenn Windrem Trucking $124,275.00 Yes
James Dick Aggregates $132,150.00 Yes
LaFarge North America $135,000.00 Yes
Nelson Aggregate Co. No Bid n/a
Strada Aggregates $146,250.00 Yes
1.3 SUPPLY & DELIVERY OF AGGREGATES
Bob Hunter Memorial Park, City of Markham
Supply & Delivery of approximately 550 tonnes of limestone screenings
Contract RSD13-085
BIDDER Total Contract Price Tender Security
(Plus HST)
Glenn Windrem Trucking $8,563.50 Yes
James Dick Aggregates $9,828.50 Yes
LaFarge North America $9,625.00 Yes
Nelson Aggregate Co. No Bid n/a
Strada Aggregates $9,762.50 Yes
IT WAS AGREED AND RECOMMENDED THAT the tender received as listed above be referred
to staff for review.
/ks
13
0)111114\1"4
Toronto and Region
sW Conservation
Authority
MEETING OF THE TENDER OPENING COMMITTEE #8/13
June 21, 2013
The Tender Opening Committee Meeting #8/13, was held in Weston Room B, Black
Creek Pioneer Village, on Friday, June 21, 2013. The Chair Gerri Lynn O'Connor, called
the meeting to order at 11:30 a.m.
PRESENT
James Dickie Supervisor, Procurement and Contract Management
Aaron D'Souza Project Coordinator, PMO
Lisa Moore Project Coordinator, PMO
Gerri Lynn O'Connor Chair
Mark Preston Senior Supervisor, Construction Services
Rocco Sgambelluri Chief Financial Officer
Kathy Stranks Manager, Corporate Secretariat
1. TENDER OPENING COMMITTEE
1.1 CLAREMONT FIELD CENTRE RETROFIT PROJECT
Contract PMO13-07
BIDDER Total Value of Addendums 1 & 2
Contract
(Plus HST)
(Levitt Goodman Architects $39,200.00 Yes
IMC Ardhitects No Bid n/a
ITen-2-Four Architecture Inc. $67,500.00 Yes
'Montgomery Sisam Archtects Inc. $100,795.00 Yes
14
1.4 BLUFFERS PARK PROJECT CHANNEL DREDGING - EMERGENCY WORKS
RSD13-084
BIDDERS Total Tender Addendum Bid Bond
Amount
(Plus HST)
Catalina Excavating $121,700.00 Yes Yes
Dean Construction Co. Ltd. $170,918.00 Yes Yes
Galcon Marine Ltd. $125,950.00 Yes Yes
Metric Contracting Services Co. No Bid n/a n/a
The Ontario Construction Company No Bid n/a n/a
Titanium Contracting Inc. No Bid n/a n/a
IT WAS AGREED AND RECOMMENDED THAT the tender received as listed above be referred
to staff for review.
/ks
15
0)11114\1"4
Toronto and Region
sW Conservation
Authority
MEETING OF THE TENDER OPENING COMMITTEE #9/13
July 12, 2013
The Tender Opening Committee Meeting #9/13, was held in the Duffins Room, Head
Office, on Friday, July 12, 2013. The Chair Michael Di Biase, called the meeting to order
at 11:30 a.m.
PRESENT
Michael Di Biase Member, Authority
James Dickie Supervisor, Procurement and Contract Management
Lisa Moore Project Coordinator, PMO
Rocco Sgambelluri Chief Financial Officer
Kathy Stranks Manager, Corporate Secretariat
Albert Thomas Contract Coordinator, Procurement and Contract Management
1. TENDER OPENING COMMITTEE
1.1 ALBION HILLS CONSERVATION AREA GATEHOUSE CONSTRUCTION
PROJECT
Contract PMO13-05
BIDDER Total Tender Addendum Tender Deposit
Amount Acknowledgement 10% (Bid Bond
(Plus HST) or Certified
Cheque)
Ameresco Canada Inc. $583,500.00 Yes Yes
Dineen Construction Corporation No Bid n/a n/a
J.D. Strachan Construction Limited $658,300.00 Yes Yes
Martinway Contracting Limited $931,193.00 Yes Yes
Morosons Construction Limited $1,245,000.00 1 to 2 only Yes
Silver Birch Contracting Limited $534,800.00 Yes Yes
Snyder Construction $694,900.00 Yes Yes
Steelcore Construction Limited $722,590.00 Yes Yes
IT WAS AGREED AND RECOMMENDED THAT the tender received as listed above be referred
to staff for review.
/ks
16
0)111114\1"4
Toronto and Region
sW Conservation
Authority
MEETING OF THE TENDER OPENING COMMITTEE #10/13
July 22, 2013
The Tender Opening Committee Meeting #10/13, was held in the Humber Room, Head
Office, on Monday, July 22, 2013. The Chair Maria Augimeri, called the meeting to order
at 11:15 a.m.
PRESENT
Maria Augimeri Vice Chair, Authority
James Dickie Supervisor, Procurement and Contract Management
Wendy Rowney Acting General Manager, Black Creek Pioneer Village
Albert Thomas Contract Coordinator, Procurement and Contract Management
Rocco Sgambelluri Chief Financial Officer
Kathy Stranks Manager, Corporate Secretariat
1. TENDER OPENING COMMITTEE
1.1 ALBION HILLS CONSERVATION AREA FIELD CENTRE PHASE 5 RETROFIT
PROJECT
MECHANICAL, ELECTRICAL AND WASHROOM UPGRADE
RFT - PMO13-06
BIDDER Total Tender Addendum Tender Deposit 10%
Amount Acknowledged (Bid Bond or
(Plus HST) Certified Cheque)
lAmeresco Canada Inc. 1 ,456,546.00 Yes Yes
IBerkim Construstion Inc. 1 ,374,092.00 Yes Yes
J.D. Strachan Construction No Bid n/a n/a
Limited
IMartinway Contracting 975,940.00 Yes Yes
Limited
IMorosons Construction No Bid n/a n/a
Limited
(Silver Birch Contracting No Bid n/a n/a
Limited
(Snyder Construction No Bid n/a n/a
ISteelcore Construction No Bid n/a n/a
Limited
17
1.2 BLACK CREEK PIONEER VILLAGE VISITOR CENTRE GENERATOR
PROJECT
GENERATOR INSTALLATION WORKS
BIDDER Total Tender Addendum Tender Deposit 10%
Amount Acknowledgement (Bid Bond or
(Plus HST) Certified Cheque)
Cummins Eastern Canada No Bid n/a n/a
Dilisado Enterpirses 499,000.00 Yes Yes
Ferguson Electrical 327,700.00 Yes Yes
Gal Power System No Bid n/a n/a
Kenstruct Limited 851,890.08 Yes Yes
Paramount Systems Limited No Bid n/a n/a
(Platinum Electrical 379,750.00 Yes Yes
Contracting
'Superior Boiler Works & 290,459.00 Yes Yes
Welding Ltd.
ITotal Power No Bid n/a n/a
ITri-Phase Group No Bid n/a n/a
lUnited Contracting No Bid n/a n/a
IWajax Power Systems No Bid n/a n/a
1.3 PORT UNION WATERFRONT PARKING LOT
PARKING LOT CONSTRUCTION
RSD13-096
BIDDERS Total Tender Addendum
Amount Acknowledgement
(Plus HST)
Appco Paving No Bid n/a
CLS Group No Bid n/a
Dynex Construction No Bid n/a
Four Seasons Site Development 70,000.00 Yes
LocPav Construction Ltd. 69,900.00 Yes
Lomco Contracting 87,980.00 Yes
McPherson-Andrews Contracting No Bid n/a
Mopal Construction 215,002.00 Yes
Pacific Paving 94,950.00 Yes
Serve Construction 118,200.00 Yes
TBG Landscape Inc. No Bid n/a
IT WAS AGREED AND RECOMMENDED THAT the tender received as listed above be referred
to staff for review.
/ks
18
0)111114\1"4
Toronto and Region
sW Conservation
Authority
MEETING OF THE TENDER OPENING COMMITTEE #11/13
July 26, 2013
The Tender Opening Committee Meeting #11/13, was held in Weston Room B, on Friday,
July 26, 2013. The Chair Maria Augmeri, called the meeting to order at 8:57 a.m.
PRESENT
Maria Augimeri Vice Chair, Authority
James Dickie Supervisor, Procurement and Contract Management
Patricia Newland Project Manager, Environmental Engineering Projects
Rocco Sgambelluri Chief Financial Officer
Kathy Stranks Manager, Corporate Secretariat
1. TENDER OPENING COMMITTEE
1.1 4180 to 4190 DUNDAS STREET WEST, CITY OF TORONTO
Detailed Design of Slope Stabilization and Erosion Control Works
RSD13-087
BIDDER Bid Amount
(Plus HST)
A.W. Hooker Associates Ltd. - Cost Consultant No Bid
AME Materials Engineering No Bid
AMEC Earth & Environmental $99,040.00
Aquafor Beech Limited No Bid
BGC Engineering Inc. No Bid
CIC Contractors Inc. No Bid
Civica Infrastructure Inc. No Bid
Coffey Geotechnics Inc. No Bid
Cole Engineering Group Ltd. $18,561.50
Dessau / LVM No Bid
EXP Service Inc. No Bid
GeoTerre Limited No Bid
Golder Associates Ltd. No Bid
Groundwork Engineering Limited No Bid
Hatch No Bid
LGL Limited Environmental Research Associates No Bid
LVM $36,312.00
19
Bid Results Continued
BIDDER Bid Amount
(Plus HST)
Natural Resource Solutions Inc. No Bid
Palmer Environmental Consulting Group No Bid
Sarafinchin Associates Ltd. No Bid
Shoreplan Engineering Ltd. No Bid
Soil Probe Consulting Engineers $43,100.00
SPL Consultants Limited No Bid
Stantec Architecture Ltd., Architects No Bid
Stantec Consulting Ltd. $37,090.00
T2 Utility Engineers No Bid
Terraprobe Inc. $38,400.00
The Sernas Group Inc. (A GHD Company) No Bid
URS Canada Inc. No Bid
Water's Edge No Bid
IT WAS AGREED AND RECOMMENDED THAT the tender received as listed above be referred
to staff for review.