HomeMy WebLinkAboutFlood Control & Water Conservation Advisory Board 1978C -1 the metropolitan toronto and region conservation authority minutes FLOOD CONTROL & WATER CONS. ADV. BD. THURSDAY- MARCH -30 -1978 #1/78 The Flood Control and Water Conservation Advisory Board met in the Board Room, Authority Office, 5 Shoreham Drive, Downsview, on Thursday, March 30, 1978, commencing at 1:30 p.m. PRESENT WERE Chairman Members Chairman of the Authority Vice Chairman of the Authority Chairman, R.D.H.P. Adv.Bd. Director of Planning & Policy Adm. - Water Resource Division Head, F/C Section WRD Project Engineer F/C Section WRD Engineer, F/C Section WRD Development Supervisor F/C WRD Research Planner P & P Project Planner WRD Project Biologist WRD ABSENT WERE Vice Chairman Members J.S. Scott Wm. Baillie F.J. Brown R. Fitzpatrick C.F. Kline L. Martin F.J. McKechnie A. Tonks H.G. Westney R. Grant Henderson Mrs. F. Gell Mrs. S. Martin W.A. McLean M.R. Garrett J.C. .Mather A. Sahabandu R. Saadia R. Dewell Mrs. A.C. Deans T.E. Farrell I.D. Macnab MINUTES The Minutes of Meeting #4/77 were presented. Res. 1 Moved by: Seconded by: RESOLVED THAT: adopted. Wm. R. Herridge, Q.C. Wm. G. Barber G. Risk A.M. Robertson J. Sewell C.F. Kline R. Fitzpatrick The Minutes of Meeting #4/77, as presented, be CARRIED; STAFF PROGRESS REPORT The staff presented a verbal report on the progress being made on the 1978 programme of the Flood Control and Water Conservation Advisory Board. Res. #2, Moved by: Seconded by: H.G. Westney Wm. Baillie C -2 -2- RESOLVED THAT: The verbal Staff Progress Report, as presented, be received. CARRIED; COMMUNICATION FROM THE BOROUGH OF NORTH YORK COUNCIL re Erosion - 12 Bruce Farm Drive German Mills Creek (Don) The staff presented a report regarding the staff investigation concerning erosion in the Don River Watershed on Bruce Farm Drive. Res. #3 Moved by: Wm. Baillie Seconded by: L. Martin RESOLVED THAT: The staff report regarding erosion on Bruce Farm Drive, German Mills Creek, Don River Watershed, as amended by referring to Numbers 8 - 12 Bruce Farm Drive, be received; and THE BOARD RECOMMENDS THAT: The Council of the Borough of North York be advised: (a) THAT The Metropolitan Toronto and Region Conservation Authority undertakes major remedial work for erosion control on a priority basis; (b) THAT the priorities are reviewed regularly and revised on an annual basis; (c) THAT this site was visited in November, 1977, to assess recent changes; (d) THAT the erosion problem at the rear of Numbers 8 - 12 Bruce Farm Drive has been given a ranking of technical priority #21 in the Authority's revised list of priorities for 1978; and further THAT the staff be directed to advise the Borough of North York of the probable timing of work based on this ranking. CARRIED; EROSION CONTROL - HIGHLAND CREEK Nos. 62 - 66 Creekwood Drive Vicinity Borough of Scarborough The staff presented a report concerning the investigation of erosion problems on Creekwood Drive, Borough of Scarborough. Res. ##4 Moved by: Mrs. F. Gell Seconded by: Wm. Baillie RESOLVED THAT: The staff report regarding the investigation of erosion problems on Creekwood Drive, Borough of Scarborough, be received; and THE BOARD RECOMMENDS THAT: The erosion control work behind Nos. 62, 64 and 66 Creekwood Drive, Borough of Scarborough, Highland Creek Watershed, be carried out under Project W.C.75 - Channel Improvements on the Highland Creek - at a cost estimated to be $14,700.00; and THAT the reinstitution of the existing check dam be not carried out until completion of the hydrologic model study; and further -3- C -3 THAT the staff be directed to advise the Borough of Scarborough Council and Mr. W. Burrell of the proposed timing of work on this site. CARRIED; REPORT RE 1977 WATERSHED ENVIRONMENTAL MONITORING PROGRAMME AND OUTLINE OF 1978 PROGRAMME The staff presented a report reviewing the Watershed Environmental Monitoring Programme for 1977 and outlining the programme for 1978. Res. #5 Moved by: Seconded by: C.F. Kline Wm. Baillie RESOLVED THAT: The staff communication "Report on the 1977 Water- shed Environmental Monitoring Programme and Outline of the 1978 Programme" be received for information. CARRIED; INTERIM PLAN - WATER & RELATED LAND MANAGEMENT The staff presented a report "Interim Plan - Water & Related Land Management ", summarizing existing policies and programmes of the Authority relating to water and land management, describing physical characteristics of the watersheds, existing land use, and demands on the watershed, and recommending management policies. Res. #6 Moved by: C.F. Kline Seconded by: Wm. Baillie RESOLVED THAT: The Interim Plan - Water & Related Land Management, The Metropolitan Toronto and Region Conservation Authority, January, 1978, be received; and THE BOARD RECOMMENDS THAT: The Interim Plan - Water & Related Land Management, The Metropolitan Toronto and Region Conservation Authority, January, 1978 be forwarded to The Province of Ontario and to the municipalities within the Authority's area of jurisdiction as supporting information for the Interim Water and Related Land Management Project, and for comment. Amendment Moved by: L. Martin Seconded by: F.J. McKechnie THAT Section 4.3.6. be added; to read: The role of the resources as a valuable natural component of the landscape be recognized. NOT CARRIED; RESOLUTION #6 CARRIED; INTERIM WATER AND RELATED LAND MANAGEMENT PROJECT The staff presented S report - The Metropolitan Toronto and Region Conservation Authority Interim Water and Related Land Management Project, which provides for the consolidation of existing Authority Water and Related Ltd Management Projects and the addition of Erosion Control and-'Bank Stabilization Works for a three -year period, 1979 - 1981 inclusive. C -4 -4- Res. #7 Moved by: F.J. McKechnie Seconded by: A. Tonks RESOLVED THAT: The Report - The Metropolitan Toronto and Region Conservation Authority Interim Water and Related Land Management Project, as amended, be received; and THE BOARD RECOMMENDS THAT: The Metropolitan Toronto and Region Conservation Authority Interim Water and Related Land Management Project for the period 1979 -1981 inclusive, dated March, 1978, as amended, for a total amount of $11,400,000.00, be adopted; and THAT the following action be taken in connection therewith: (a) The Regions of Peel, York and Durham, The Municipality of Metropolitan Toronto and the Townships of Adjala and Mono be designated as the benefiting municipalities on the basis set forth in the Project; (b) The Government of The Province of Ontario be requested to approve the Project and a grant of 55% of the cost thereof; (c) Where required, the Ontario Municipal Board be requested to approve the Project pursuant to Section 23 of The Conservat- ion Authorities Act; (d) When approved, the appropriate Authority officials be authorized to take whatever action is required in connection with the Project, including the execution of any necessary documents. CARRIED; MULTI -YEAR FORECAST - 1980 -1983 The staff presented a report outlining the Multi -Year Forecast for the period 1980 -1983, as required by The Province of Ontario. Res. #8 Moved by: F.J. McKechnie Seconded by: C.F. Kline RESOLVED THAT: The Multi -Year Budget Forecast for 1980 -1983 be received; and THE BOARD RECOMMENDS THAT: The Multi -Year Budget Forecast for the period 1980 -1983 for the Flood Control Section, Water Resource Division, dated March 30, 1978, be approved in principle and included in the 1980 -1983 Multi -Year Forecast of the Authority. CARRIED; HYDROLOGIC MODELLING STUDY OF THE ETOBICOKE CREEK AND MIMICO CREEK The staff advised that the Hydrologic Modelling Study of the Etobicoke Creek and the Mimico Creek had just been received and the report was circulated for the information of the Board Members. Res. #9 Moved by: C.F. Kline Seconded by: F.J. McKechnie RESOLVED THAT: The Hydrologic Modelling Study of the Etobicoke Creek and the Mimico Creek be received; and THAT copies of the Study be circulated to Members of the Board not present at this meeting; to the staffs of The Regional Municipality of Peel, the Cities of Brampton and Mississauga, and to the Borough of Etobicoke, for technical comment; and further; -5- C -5 THAT the Flood Control and Water Conservation Advisory Board meet on Thursday. May 11, 1978, commencing at 1:30 p.m., in the Humber Room, Authority Office, 5 Shoreham Drive, Downsview, to consider the Study. CARRIED; ADJOURNMENT On Motion, the Meeting adjourned at 5:15 p.m., March 30. J.S. Scott W.A. McLean, Dir. - Planning & Policy Chairman Acting Secretary- Treasurer ts. er FC&WC C -6 ET -MIM L -1 the metropolitan toronto and region conservation authority minutes FLOOD CONTROL & WATER CONS. ADV. BOARD FCWC #2/78 ETOBICOKE- MIMICO ADVISORY BOARD THURSDAY- MAY -11 -1978 E -M #1/78 The Flood Control and Water Conservation and the Etobicoke - Mimico Advisory Boards met in joint session at the Authority Office, 5 Shoreham Drive, Downsview, on Thursday, May 11, 1978, commencing at 1:30 p.m. PRESENT - FLOOD CONTROL & WATER CONSERVATION ADVISORY BOARD Chairman Vice Chairman Chairman of the Authority Authority Member Secretary- Treasurer Director of Planning & Policy Adm. - Water Resource Division Head -Flood Control Section, WRD Research Planner, Planning & Policy Project Engineer -Flood Control, WRD Engineer -Flood Control Section, WRD Project Planner - WRD Project Biologist - WRD Borough Engineer - Borough of Etobicoke James F. MacLaren Limited Consulting Engineers ABSENT WERE Members PRESENT - ETOBICOKE- MIMICO ADVISORY BOARD Chairman Vice Chairman Chairman of the Authority Authority Member Secretary- Treasurer Director of Planning & Policy Adm. - Water Resource Division Head -Flood Control Section, WRD Research Planner, Planning & Policy Project Engineer -Flood Control, WRD Engineer -Flood Control Section, WRD Project Planner - WRD Project Biologist - WRD Borough Engineer - Borough of Etobicoke James F. MacLaren Limited Consulting Engineers J.S. Scott Wm. R. Herridge, Q.C. Wm. Baillie Wm. G. Barber F.J. Brown C.F. Kline L. Martin F.J. McKechnie A. Tonks R. Grant Henderson Mrs. S. Martin R.G. Higgs W.A. McLean M.R. Garrett J.C. Mather Mrs. A.C. Deans A.G. Sahabandu R. Saadia T.E. Farrell I.D. Macnab W.M. Swann R. Wigle R. Fitzpatrick G. Risk A.M. Robertson J. Sewell H.G. Westney C.F. Kline F.J. McKechnie Wm. Baillie Mrs. N. Pownall R. Grant Henderson Mrs. S. Martin R.G. Higgs W.A. McLean M.R. Garrett J.C. Mather Mrs. A.C. Deans A.G. Sahabandu R. Saadia T.E. Farrell I.D. Macnab W.M. Swann R. Wigle FC &WC C -7 ET -MIM L -2 ABSENT WERE Members -2- R.F. Bean M.J. Breen T.W. Butt G.B. Sinclair Mr. Scott advised of the death, on April 30, 1978, of Mr. John Carroll, former Chairman of the Flood Control and Water Conservation Advisory Board. Res. #10 (FC &WC) Moved by: Wm. R. Herridge, Q.C. Seconded by: F.J. McKechnie RESOLVED THAT: The Chairman of the Authority be requested to forward a letter of sympathy to the family of Mr. John Carroll, former Chairman of the Flood Control and Water Conservation Advisory, expressing the profound regret of the Board in the loss of Mr. Carroll. CARRIED; MINUTES The Minutes of Flood Control and Water Conservation Advisory Board Meeting #1/78 were presented. Res. #11 (FC &WC) Moved by; C.F. Kline Seconded by: Wm. Baillie RESOLVED THAT: The Minutes of Meeting #1/78, as presented, be adopted. CARRIED; The Minutes of the Etobicoke - Mimico Advisory Board Meeting #2/77 were presented. Res. #1 (E -M) Moved by: F.J. McKechnie Seconded by: Wm. Baillie RESOLVED THAT: The Minutes of Meeting #2/77, as presented, be adopted. CARRIED; STAFF PROGRESS REPORT The staff presented a verbal progress report on the activities of the Water Resource Division. Res. #12 (FC &WC) Moved by: Wm. G. Barber Seconded by: A. Tonks RESOLVED THAT: That the verbal staff progress report on Flood Control and Water Conservation be received. CARRIED; LINEAR PARK CONCEPT FOR MIMICO CREEK -Use of Erosion Control Work for Pedestrian Access The staff presented a report and recommendations on the Linear Park Concept for Mimico Creek - Use of Erosion Control Work for Pedestrian Access. Res. #13 (FC &WC) Moved by: Wm. Baillie Seconded by: A. Tonks RESOLVED THAT: The report and recommendations on the Linear Park Concept for Mimico Creek - use of Erosion Control Work for Pedestrian Access, be received; and -3- THAT the recommendations contained therein be approved. INTERIM WATER AND RELATED LAND MANAGEMENT PROJECT: 1979 -1981 - Channel Improvements on the Duffin Creek in the Town of Whitchurch-Stouffville FC &WC C -8 ET-MIM L-3 CARRIED; The staff presented a report on proposed channel improvements on the Duffin Creek in the Town of Whitchurch- Stouffville. Res. #14 (FC &WC) Moved by: C.F. Kline Seconded by: Wm. G. Barber RESOLVED THAT: The report on channel improvements on the Duffin Creek in the Town of Whitchurch - Stouffville be received; and THE BOARD RECOMMENDS THAT: The following action be taken in regard to the Interim Water and Related Land Management Project: 1979 -1981 - Channel Improvements on the Duffin Creek in the Town of Whitchurch- Stouffville: (a) The works outlined in the brief: "Channel Improvements on the Duffin Creek in the Town of Whitchurch- Stouffville ", dated April 28, 1978, be approved; (b) The Regional Municipality of York be requested to approve the work proposed in the brief on "Channel Improvements on the Duffin Creek in the Town of Whitchurch - Stouffville ", dated April 28, 1978; (c) The Regional Municipality of York be advised that, subject to the approvals required for the Interim Water and Related Land Management Project 1979 -1981 being obtained, the Authority is prepared to proceed with the channel improvements on the Duffin Creek in the Town of Whitchurch- Stouffville, as set out in the brief dated April 28, 1978, on the basis of funding provided for in the Project for these works. CARRIED; WATER AND RELATED LAND MANAGEMENT PLAN UPDATE- - Etobicoke- Mimico Watershed Study The staff presented for the consideration of the Boards a preliminary report for discussion on the Etobicoke- Mimico Watershed Study and the Water and Related Land Management Plan Update. Res. #15 (FC &WC) Moved by: F.J. McKechnie Seconded by: L. Martin RESOLVED THAT: The staff reports on the Etobicoke - Mimico Watershed Study and the Water and Related Land Management Plan Update be received; and THAT these reports be considered at a future meeting of the Flood Control and Water Conservation Advisory Board. NEW BUSINESS ONTARIO REGULATION 735/73 -Fill, Construction and Alteration to Waterways A discussion took place regarding the provision of notices to municipalities of applications for permits under Ontario Regulation 735/73. FC &WC C -9 ET -MIM L -4 Res. #16 (FC &WC) -4- Moved by: F.J. McKechnie Seconded by: Wm. R. Herridge, Q.C. THE BOARD RECOMMENDS THAT: The Clerks of the affected municipalities be advised forthwith of all applications for permits under Ontario Regulation 735/73: Regulation made under The Conservation Authorities Act - Fill, Construction and Alteration to Waterways, upon receipt of such applications. ON A RECORDED VOTE, VOTING IN THE: AFFIRMATIVE NEGATIVE J.S. Scott Wm. R. Herridge, Q.C. L. Martin F.J. McKechnie Wm. Baillie Wm. G. Barber F.J. Brown THE MOTION CARRIED; ADJOURNMENT On Motion, the meeting adjourned at 4:45 p.m. J.S. Scott K.G. Higgs Chairman Secretary- Treasurer er the metropolitan toronto and region conservation authority minutes C-10 FLOOD CONTROL & WATER CONS. ADV. BOARD THURS- AUGUST -31 -1978 #3/78 The Flood Control and Water Conservation Advisory Board met at the Authority Office, 5 Shoreham Drive, Downsview, on Thursday, August 31, 1978, commencing at 1:30 p.m. PRESENT WERE Chairman Vice Chairman Chairman of the Authority Vice Chairman of the Authority Authority Member Secretary - Treasurer Adm. - Water Resource Division Head -Flood Control Section, WRD. Project Engineer -Flood Control Section, WRD Engineer -Flood Control Section, WRD Maint. & Ops. Spvr.,Flood Control Section, WRD Development Co- ordinator, Planning & Policy ABSENT WERE Members MINUTES The Minutes of Meeting #2/78 were presented. J.S. Scott Wm. R. Herridge, Q.C. Wm. Baillie Wm. G. Barber F.J. Brown R. Fitzpatrick C.F. Kline L. Martin A. Tonks R. Grant Henderson Mrs. F. Gell Mrs. S. Martin K.G. Higgs M.R. Garrett J.C. Mather A.G. Sahabandu R. Saadia R.W. Dewell J.W. Maletich F.J. McKechnie G. Risk A.M. Robertson J. Sewell H.G. Westney Res. #17 Moved by: Wm. G. Barber Seconded by: R. Fitzpatrick RESOLVED THAT: The Minutes of Meeting #2/78, as presented, be adopted. CARRIED; PROGRESS REPORT Mr. J.C. Mather, Head of the Flood Control Section, Water Resource Division, presented a Progress Report, outlining the status of the following: - Flood Control and Water Conservation Maintenance Programme - Flood Warning and Forecasting System - Flood Control Plan - Environmental Monitoring Programme - Status of works being carried out under Project W.C. -60 c -11 Res. #18 -2- - Status of the work on the Highland Creek under Prajedt,,W.C. -75 - Status of the Study on the East Branch of the Humber4:1i2iver at Oak Ridges. Moved by: Wm. Baillie Seconded by: F.J. Brown RESOLVED THAT: The Progress Report, as presented, be received. DELEGATION - MR. C.D. REBURN Res. #19 CARRIED; Moved by: Wm. R. Herridge, Q.C. Seconded by: A. Tonks RESOLVED THAT: The delegation of Mr. C. Dudley Reburn be heard. CARRIED; Mr. Reburn outlined the continuing problem of erosion on his property at 91 Forest Grove Drive, Willowdale (Borough of North York). He advised that the situation had worsened since he last appeared before the Board in October of 1977. Mr. Reburn stated he had been advised by a real estate appraiser that the value of his property was affected by the erosion, and photographs were distributed to the members, showing the extent of erosion on his land. He further stated that he was of the opinion that the work carried out upstream by the Authority had had an adverse effect on his property. Mr. Reburn was advised that, on the basis of the present priority ratings his erosion problem was #13. Res. #20 Moved by: A. Tonks Seconded by: Wm. R. Herridge, Q.C. RESOLVED THAT: The staff be requested to obtain a legal opinion on the Authority's responsibility with respect to the erosion on the property of Mr. C. Dudley Reburn, 91 Forest Grove Drive, Borough of North York. CARRIED; Res. #21 Moved by: A. Tonks Seconded by: Wm. G. Barber RESOLVED THAT: The staff be requested to inform Mr. Reburn of the status of the erosion on his property. CARRIED; PRELIMINARY BUDGET ESTIMATES - 1979 The 1979 Preliminary Budget Estimates were presented. Res. #22 Moved by: C.F. Kline Seconded by: A. Tonks RESOLVED THAT: The 1979 Preliminary Budget Estimates for the Water Resource Division, Flood Control Section, dated 1978.08.18, be approved in principle; and THE BOARD RECOMMENDS THAT: The 1979 Preliminary Budget Estimates for the Flood Control Section, Water Resource Division, as appended as Schedule "A" of these Minutes, be included in the 1979 Preliminary Budget Estimates of the Authority. CARRIED; -3- C -12 INTERIM WATER & RELATED LAND MANAGEMENT PROJECT 1979 -1981 Erosion Control and Bank Stabilization in Metropolitan Toronto (formerly Project W.C. -60) - Progress Report, Erosion Inventory, Current Priorities, 1979 Work Programme The staff presented a report having regard to Project W.C. -60, out- lining the accomplishments to date, the erosion inventory by water- shed, current priorities and the 1979 work programme. Res. #23 Moved by: C.F. Kline Seconded by: Wm. G. Barber RESOLVED THAT: The Progress Report and the Erosion Inventory on Project W.C. -60 be received and appended as part of Schedule "B" of these Minutes; and THE BOARD RECOMMENDS THAT: The 1979 Work Programme and the Current Priorities for Erosion Control and Bank Stabilization in Metropolitan Toronto, as appended as part of Schedule "B" of these Minutes, be approved. CARRIED; Res. #24 Moved by: A. Tonks Seconded by: F.J. Brown RESOLVED THAT: The staff be requested to prepare a report on the status of Technical Priority #17, 50 -58 Dennison Avenue, Humber River Watershed, Borough of York, and to forward a copy of the report to the Engineer of the Borough of York. CARRIED; INTERIM WATER & RELATED LAND MANAGEMENT PROJECT 1979 -1981 Erosion Control and Bank Stabilization in the Regional Municipalities of Peel, York and Durham - 1979 Programme The staff submitted a report outlining the 1979 Work Programme and the Current Priorities for the Regional Municipalities of Peel, York and Durham. Res. #25 Moved by: Wm. Baillie Seconded by: R. Fitzpatrick RESOLVED THAT: The report on Erosion Control and Bank Stabilization in the Regional Municipalities of Peel, York and Durham, be received; and THE BOARD RECOMMENDS THAT: The 1979 Work Programme and Current Priorities for the Regional Municipalities of Peel, York and Durham, as appended as Schedule "C" of these Minutes, be approved. Res. #26 Moved by: Seconded by: CARRIED; Wm. R. Herridge, Q.C. Wm. Baillie RESOLVED THAT: The staff be requested to prepare a detailed report on Technical Priority #6 in The Regional Municipality of York, 8240 Pine Valley Drive, Humber River Watershed, Town of Vaughan; and THAT the staff be requested to review the policy of the Authority regarding the Erosion Control and Bank Stabilization Programme and to submit a report and recommendations for the consideration of the Board. CARRIED; INTERIM WATER & RELATED LAND MANAGEMENT PROJECT 1979 -1981 A discussion took place regarding the status of the Interim Water and Related Land Management Project 1979 -1981. C -13 -4- The Board was advised that the Project has been approved by The Municipality of Metropolitan Toronto, The Regional Municipalities of Peel and York, and that The Regional Municipality of Durham is appeal- ing the levy for the Project. The Project has been submitted to the Ministry of Natural Resources, it is hoped that Ministerial approval will be received prior to the end of September, 1978, and that a meeting of the Ontario Municipal Board will be scheduled following approval by the Minister. COMMUNICATION FROM MARY SMITH The Board reviewed a communication from Mary Smith regarding suggestions for the work being undertaken by the Authority under Project W.C. -75 (Highland Creek). Res. #27 Moved by: Wm. G. Barber Seconded by: Wm. Baillie RESOLVED THAT: The communication from Mary Smith be received; and THAT Mrs. Smith be thanked for her interest and constructive comments. CARRIED; SCARBOROUGH DRAINAGE POLICY The staff presented a copy of the Borough of Scarborough Drainage Policy and a copy of the Authority's staff comments on the policy. Res. #28 Moved by: Wm. R. Herridge, Q.C. Seconded by: C.F. Kline RESOLVED THAT: The Report on the Borough of Scarborough Drainage Policy be received; and THAT the Council and the Commissioner of Works of The Corporation of the Borough of Scarborough be commended for the development of the Scarborough Drainage Policy. CARRIED; NEW BUSINESS A discussion took place regarding the Water and Related Land Management Plan. The staff indicated that a detailed report of the criteria for the Plan should be available for discussion at the first meeting of the Flood Control and Water Conservation Advisory Board in 1979. A discussion took place regarding Notices of Hearings and Applications under Ontario Regulation 735/73 - Regulation made under The Conservation Authorities Act - Fill, Construction and Alteration to Waterways. Mr. Maletich outlined the procedure whereby municipalities receive Notices of Hearings and copies of Applications for Permit under the Regulation. ADJOURNMENT On Motion, the meeting adjourned at 5:00 p.m. J.S. Scott K.G. Higgs Chairman Secretary- Treasurer SCHEDULE "A" TO: The Chairman & Members of the Flood Control & Water C -14 Conservation Advisory Board, M.T.R.C.A., Meeting #3/78 RE: 1979 BUDGET ESTIMATES Attached are the Budget Estimates for 1979. They reflect the breakdown approved as part of the Interim Water and Related Land Management Project 1979 - 1981. There are three categories: (1) Interim Project -- Current (2) Interim Project -- Capital (3) Operations and Maintenance The first two -- when totalled ($3,800,000.) -- is the total Project Funding for 1979. Each of the budgets has been broken down into "All Municipalities Benefiting" and "One Municipality Benefiting ". The attached sheets explain the expenditures proposed. The Budget reflects 1978 salary levels and will require adjustment at a later date. RECOMMENDATION: THE BOARD RECOMMENDS THAT: the 1979 Budget Estimates for the Interim Water and Related Land Management Project and for the Flood Control Opeations and Maintenance of the Flood Control Section of the Water Resource Division be approved. CM /K Attachments 1978.08.18/ M. R. Garrett Administrator Water Resource Division PROGRAM 1979 CURRENT BUDGET ESTIMATES WATER & RELATED LAND MANAGEMENT - OPERATION & MAINTENANCE OF WATER CONTROL STRUCTURES (W5) PURPOSE: 1979 OBJECTIVES: FUNDING: FINANCIAL COMMENTS: OBJECTIVE CLASSIFICATIONS: 1978.08.18. To maintain Flood Control works established under the Authority's Plan For Flood Control and Water Conservation. PAGE - continuation of the regular maintenance of Flood Control works at a level comparable with that of 1978; - major maintenance to be carriedcut at Milne, Black Creek, Lower Humber, Massey Creek and Claireville; - provision for the maintenance of erosion control channels constructed under the downstream erosion control program; This is a shared program, 55% of the funds being available from The Province of Ontario and the balance being funded from the General Levy on all participating municipalities. Funding has been allocated in order to cover a progregive maintenance program, including non - recurring major maintenance. Salaries & Wages 63,500. Materials Supplies & Utilities 65,600. Equipment $.. Real Property Services & Rents 60,900. Taxes Financial Expenses Total 190,000. 1979 CURRENT BUDGET ESTIMATES PROGRAM Water and Related Land Management - Operations and Maintenance Activity Flood Warning Claireville G. Ross Lord Milne Small Dams Gen. River Channels Major Maintenance Erosion Works 1979 BUDGET Expenditures Revenues Net Expenditures 18,000 , 8,100 18,000 23,000 10,350 23,000 23,000 10,350 23,000 4,000 1,800 4,000 3,000 1,350 3,000 75,000 33,750 75,000 40,000 18,000 40,000 4,000 1,800 4,000 190,000 190,000 . . SOURCES OF FINANCING Provincial Grant Municipal Levy Other 9,900 , 8,100 12,650 10,350 12,650 10,350 2,200 1,800 1,650 1,350 41,250 33,750 22,000 18,000 2,200 1,800 1,045,000 85,500 • / , 1978 ACTUALS Expenditures Revenues . . PAGE 1978 BUDGET Expenditures Revenues 12,000 23,000 23,000 6,000 5,000 68,000 20,000 2,000 i 159,000 r 0 PROGRAM 1979 CAPITAL BUDGET ESTIMATES Water & Related Land Management -- Interim Project PURPOSE: To provide the funding required for carrying out the objectives of the Interim Water and Related Land Management Project under capital budget category and which apply to all municipalities benefiting as well as single oenefiting municipalities. 1979 OBJECTIVES: - to continue the review of the Authority's Flood Control Plan from both hydrologic and environmental aspects; FUNDING: OBJECTIVE CLASSIFICATIONS: 1978.08.18. - to continue vallyland acquisition as well as important headwater lands; - to finish engineering studies on the Wilkett Creek and Oak Ridges; - the continuation of Downstream Erosion Control in Metropolitan Toronto; - completion of the reconstruction of Highland Creek channels; - first phase of construction of the Stouffville Flood Control Channel; A 50% grant is available for pre -1978 projects and a 55% grant for post -1978 projects from The Province of Ontario and the balance being funded from the Capital levies on participating municipalities. C) PAGE Materials Salaries Supplies & Real Services Financial & Wages Utilities Equipment Property & Rents Taxes Expenses Total $ $ $ $ $ $ $ $ 410,000. 366,000. - 1,200,000. 1,211,000. - - 3,187,000. PROGRAM 1979 CAPITAL BUDGET ESTIMATES Water and Related Land Management - Interim Project Activity ALL MUN. BEN. (1) Studies (2) Env. Monitoring (3) Mapping & Plotti (4) Plan Review (5) Acquisition: Flood Plain (6) Acquisition: Headwaters ONE MUN. BEN. (1) Highland Creek (Metro) (2) Erosion Control (Metro) (3) Wilket, Creek (Metro) W.C. -58 W.C. -78 (4) Stouffville (York) '( 5) Oak Ridges (York) 197R_OR_1R / 1979 BUDGET ` Expenditures Revenues Expenditures 312,000. 140,400. 312,000. 100,000. 45,000. 100,000. g 55,000. 24,750. 55,000. 45,000. 20,250. 45,000. 1,000,000. 450,000. 1,000,000. 200,000. 90,000. 200,000. 240,000. 108,000, 240,000. 825,000. 360,000. 825,000. 10,000. 4,500, 10,000. 0 0 0 0 0 0 395,000. 177,750, 395,000. 5,000. 2,250, 5,000. 3,187,000. 3,187,000. 1 1 SOURCES OF FINANCING Provincial Grant Municipal Levy Other 171,600. 140,400. 55,000. 45,000. 60,000. 30,250. 24,750. 24,750. 20,250. 505,000. 550,000. 450,000. 110,000. 90,000. 90,000. 132,000. 108,000, 440,000. 360,000. 25,000. 5,500. 4,500, 0 0 0 0 217,250. 177,750, 2,750. 2,250, - i 1,739,100. 1,422,900 . 25,000. 1978 ACTUALS Expenditures Revenues PAGE 1978 BUDGET Expenditures Revenues 280,000. 150,000. 80,000. 60,000. 1,759,000. 400,000. 505,000. 12,000. 60,000. 90,000. 20,000. 10,000. 1 3,426,000. 1979 CURRENT BUDGET ESTIMATES PROGRAM Water & Related Land Management - Interim Project PURPOSE: 1979 OBJECTIVES: FUNDING: FINANCIAL COMMENTS: OBJECTIVE CLASSIFICATIONS: 1978.08.18. PAGE To provide the funding required for carrying out the objectives of the Interim Water and Related Land Management Project under current budget category and which apply to all municipalities benefiting as well as single benefiting municipalities. - to continue the program of the installation of a radio system in co- operation with the Ministry of Natural Resources for transmitting flood control and flood warning information; • - the installation of three Telemark stream gauges in the continuing program of stream gauge telemetery. - the administration and enforcement of water management regulations, and subdivision reviews, including salaries of enforcement offioers and subdivision review staff, travel, legal and technical support costs; - to carry out resource management practices on Authority lands and to provide Conservation Assistance Programs for private landowners; - the provision of erosion control and bank stabilization works in the Regions of Peel, York, and Durham; This is a shared program, 55% of the funds being available from The Province of Ontario and the balance being funded from the General Levy on all participating municipalities. Salaries are based on 1978 levels. Salaries & Wages 326,570 Materials Supplies & Utilities Equipment $ $ 115,800. 23,000. Real Property Services & Rents 189,630. Financial Taxes Expenses Total $ $ $ 655,000. 1979 CURRENT BUDGET ESTIMATES PROGRAM Water and Related Land Management Interim Project Activity , ALL MUN. BEN. (1) Staff Salaries (2) Staff Travel (3) Flood Warning & Forecasting System (4) Flood Control Structures (5) Regulation En- forcement (6) Conservation Services ONE MUN. BEN. (1) Erosion Control (Peel) (2) Erosion Control (York) (3) Erosion Control (Durham) 7928 fE.18. 1979 BUDGET Expenditures Revenues Net Expenditures 45,500. 20,475. 45,500. 3,000 1,350. 3,000. 23,000. 10,350. 23,000. 0 0 0 175,000. 78,975. 175,000. 206,Q00. 85,950. 206,000. 101,000. 45,000. 101,000. 75,500. 33,750. 75,500. 25,500. 11,250. 25,500. 655,000. 655,000. . . SOURCES OF FINANCING Provincial Grant Municipal Levy Other 25,025. 20,475. 1,650. 1,350. 12,650. 10,350. 0 0 96,525. 78,975. 105,050. 85,950. 15,000. 55000. 45,000. 1,000. 41,250. 33,750. 500. 13,750. 11,250. 500. . 350,900. . 287,100. • 17,000. , 1978 ACTUALS PAGE 1978 BUDGET Expenditures Revenues Expenditures Revenues , 45,345. 2,655. 23,000. 12,000. 85,000. i 321,965. SCHEDULE "B" C -21 TO: The Chairman and Members of the Flood Control & Water Conservation Advisory Board, M.T.R.C.A., Meeting #3/78 RE: EROSION CONTROL AND BANK STABILIZATION IN METROPOLITAN TORONTO 1979 PROGRAMME -- PROGRESS REPORT, EROSION INVENTORY, CURRENT PRIORITIES AND 1979 WORK PROGRAMME Submitted herewith is a staff report outlining the accomplishments to date, the erosion inventory by watershed, the current priorities and the 1979 work programme. RECOMMENDATION: IT IS RECOMMENDED THAT: The 1979 Work Programme and the Current Priorities for Erosion Control and Bank Stabilization in Metro- politan Toronto be approved; and further THAT the Progress Report and the Erosion Inventory be received. AS /K M. R. Garrett Attch. Administrator Water Resource Division 1978.08.17. C -22 EROSION CONTROL AND BANK STABILIZATION IN METROPOLITAN TORONTO 1979 PROGRAMME The Metropolitan Toronto and Region Conservation Authority August 1978. C -23 EROSION CONTROL AND BANK STABILIZATION IN METROPOLITAN TORONTO 1979 PROGRAMME INTRODUCTION: The purpose of this report is to outline the progress of Project W.C. -60, which is designed to carry out the following: (a) Major erosion control and bank stabilization remedial works on a priority basis for the primary watercourses; (b) Initiate a preventative programme in the form of minor remedial works and re- vegetation of embankments. Since site conditions change continually, the priorities have to be re- viewed on a regular basis. The current top priorities are reflected in the work programme for 1979 and the "Pool of Erosion Priority Sites" for 1980, which are found in the respective sections of this report. It should be noted that the present 5 -year project terminates at the end of this year (1978). Commencing 1979, the erosion control and bank stabilization programme for Metropolitan Toronto will be expanded in keeping with the proposed increase in the annual budget for this programme. The budget allocation for this programme, which is a component within the Authority's "Interim Water and Related Land Management Project ", has $800,000. for each of the years 1979 and 1980, and $850,000. for 1981. The expanded programme for 1979 has enabled an increase in the minor remedial work component, thereby providing for a strong preventative programme. It is hoped that the preventative programme can be bolstered even further in the years following 1979. 2 PROGRESS REPORT: C -24 The following is a list of sites at which major or minor remedial work was carried out between September 1974 (incpetion of project) and September, 1978: LOCATION WATERSHED WORK YEAR Major Remedial Works 90 Forestgrove Dr. 20 -30 Islay Court 39 -41 Storer Drive 99 -103 Burbank Drive Hi Mount Drive 8 -10 King Maple Place 113 Burbank Drive 14 -22 Archway Cres. 6 Woodhaven Heights 45 Riverbank Dr. & Vic. 32 -38 Bonnyview Drive 37 -43 Lakeland Drive Yvonne Public School 30 -56 Grovetree Road 95 -97 Portico Dr. 197 -205 Sweeney Dr. 24 Stonegate Road 24 -36 Westleigh Cres. 158 -168 & 190 -212 Three Valleys Drive 6 -14 Sulkara Court Don Valley Dive Minor Remedial Works 520 Markham Rd. Vicinity (Cedarbrook Retirement Home) 84 -89 Greenbrook Drive Kirkbradden Road West Hill Collegiate Shoreham Court 27 -31 Ladysbridge Drive N/W of 56 Grovetree Rd. 37 -43 Mayall Avenue 79 Clearview Heights S/W of Shoreham Dr. Bridge Driftwood Court 75 Decarie Circle 4 Woodhaven Heights 73 Van Dusen Boulevard Donalda Club (8th Fwy.) Westleigh Crescent Vic. East Don River Humber River Humber River ,Newtonbrook Creek Newtonbrook Creek Newtonbrook Creek Newtonbrook Creek Humber River Humber River Mimico Creek Mimico Creek West Humber Black Creek West Humber E. Br. Highland Cr. East Don River Humber River Etobicoke Creek East Don River East Don River Don River Highland Creek Black Creek Mimico Creek Highland Creek Black Creek 1974 1974 1974 -1975 1974 -1975 1974 -1975 1974 -1975 1975 1975 1975 1975 1975 1975 -1976 1976 1976 1976 1976 1976 -1977 1976 -1977 1976 -1977 1978 (in progress) 1978 (in progress) 1975 1975 1975 1975 1975 W. Br. Highland Creek 1975 -1976 1975 -1976 1976 1976 1976 1976 1976 1977 1977 1978 1978 West Humber River Black Creek Black Creek Black Creek Black Creek Mimico Creek Humber River Mimico Creek Don River Etobicoke Creek C -25 - 3 EROSION INVENTORY: The following table indicates the erosion inventory for the primary watercourses within Metropolitan Toronto. Tbese sites have been identified by design block, where the Authority is either aware of a significant erosion problem or has requests for assistance in erosion control and /or bank stabilization MUNICIPALITY WATERCOURSE NO. OF SITES TOTAL Metroplitan Toronto Etobicoke Creek Mimico Creek Humber River - Don River Main Branch - West Branch - Emery Creek - Black Creek - Main Branch - West Branch - East Branch 11 35 50 10 5 21 25 35 47 - Massey Creel 15 - German Mill 4 Highland Creek Rouge River - Centennial - Main Branch - West Branch - East Branch 2 11 10 9 - Main Branch 78 - Little Rouge 27 11 35 86 126 32 105 TOTAL NO. OF SITES 395 4 CURRENT PRIORITIES: C -26 Due to the large number of sites requiring erosion control and bank stabilization work throughout Metropolitan Toronto, major remedial work is being undertaken on a priority basis. The original priority ratings listed in the James F. MacLaren report of March, 1970, are used as a starting point in assessing the rate of progress and deterioration during the nine years that have elapsed. Based on year -round monitoring, the severity of tb: problem in its present state and a fair idea of its relative potential to deteriorate, the staff has determined a pool of sites bearing high priority ratings. Because erosion is a dynamic problem, the priorities within this pool change continually as we strive to ameliorate the list with the steady influx of technical data on site conditions. Therefore, the following list of "current priorities" will be reviewed regularly during 1979 in order to accommodate any significant changes and the possible inclusion of new sites. PROPOSED MAJOR REMEDIAL WORK SITES FOR 1979 LOCATION WATERSHED BOROUGH TECHNICAL PRIORITY ESTIMATED COST COMMENTS N 35 Canyon Avenue West Don River North York 1 $260,000 Problem: Riverbank Erosion and Slope Failure Structures Affected: One apartment Complex Height of Bank: 110 ft. (34m) Length of Bank: 110 ft. (34m) 10 Codeco Court & Vicinity East Don River North York 2 $170,000 Problem: Riverbank Erosion and Slope Failure Structures Affected: One Industrial Complex (U.E. Union Complex) Height of Bank: 90 ft. (27m) Length of Bank: 180 ft. (55m) 50 -58 Stanwood Crescent Humber River North York 3 $128,000 Problem: Riverbank Erosion and Slope Failure Structures Affected: Five Residences Height of Bank: 75 ft. (23m) Length of Bank: 250 ft. (76m) Enfield- Jellicoe- Sunset Vicinity Etobicoke Creek Etobicoke * $68,000 Problem: Slope Failure (Exposed Shale) and Riverbank Erosion Structures Affected: Eight Residences Height of Bank: 55 -60 ft.(18m) Length of Bank: 600 ft.(180m) POOL OF EROSION PRIORITY SITES LOCATION WATERSHED BOROUGH ECHN�cAI TpR0RITY APPROX. COST COMMENTS PROJECTED WORK YEAR 39 -49 Presley Ave. Massey Creek Scarborough 4 $75,000 Problem: Slope Failure (Fill Material) Structures Affected: Five Residences Height of Bank: 65 -70 ft. (20m) Length of Bank: 200 ft. (61m) 1980 55 Wynford Heights East Don River North York 5 $85,000 Problem: Slope Failure and Riverbank Erosion Structures Affected: Three Apartment Buildings Height of Bank: 110 ft. (34m) Length of Bank: 150 ft. (40m) 1980 8 -14 Bruce Farm Drive German Mills Creek North York 6 $45,000 Problem: Slope Failure (Fill Material) and Riverbank Erosion Structures Affected: Four Residences Height of Bank: 35 ft. (llm) Length of Bank: 150 ft. (46m) 1980 99 -107 Weir Crescent Highland Creek Scarborough 7 $80,000 Problem: Slope Failure and.Riverbank Erosion Structures Affected: Seven Residences Height of Bank: 100 ft. (30m) Length of Bank: 500 ft. (152m) 1980 Don River East York 8 $100,000 Problem: Slope Failure (Fill Material) Structures Affected: Two Apartment Buildings + One Residence Height of Bank: 100 ft. (30m) Length of Bank: 80 -100 ft. (30m) 1980 n 16 -18 Fernwood Gardens 1 N co POOL OF EROSION PRIORITY SITES LOCATION WATERSHED BOROUGH TECHNICAL PRIORITY APPROX. COST COMMENTS PROJECTED WORK YEAR 100 -104 Gwendolen Crescent West Don River North York 9 $30,000 Problem: Slope Failure and Riverbank Erosion Structures Affected: Three Residences Height of Bank: 110 ft. (34m) Length of Bank: 150 ft. (46m) 1 n �, 1D 1980 Rowntree Mills Park (Adjacent to Aviemore Drive) Humber River North York 10 $155,000 Problem: Riverbank Erosion Structures Affected: Park Pathway and Parking Lot Height of Bank: 40 ft. (12m) Length of Bank: 250 ft. (76m) 1980 31 -35 Rivercove Dr. Mimico Creek - Etobicoke 11 $50,000 Problem: Slope Failure and Riverbank Erosion Structures Affected: Four Residences Height of Bank: 45 ft. (14m) Length of Bank: 180 ft. (55m) 1980 rUUL Ur trCUJIUIN rrClUrCI I Y bI I t5 LOCATION WATERSHED BOROUGH PTECHNIC RIORITYL COMMENTS 8 -14 Azalea Court Emery Creek North York 12 Problem: Slope Failure (Fill Material) Structures Affected: Four Residences Height of Bank: 60 ft. (18m) Length of Bank: 150 ft. (46m) 91 Forestgrove Drive East Don River North York 13 Problem: Riverbank Erosion and Slope Failure Structures Affected: 1 Residence Height of Bank: 60 ft. (18m) Length of Bank: 100 ft. (30m) 69 -71 Pegasus Trail Highland Creek Scarborough 14 Problem: Slope Failure (Fill Material) Structures Affected: Two Residences Height of Bank: 30 ft. (9m) Length of Bank: 100 ft. (30m) 18 -20 Skipton Court Black Creek North York 15 Problem: Slope Failure (Fill Material) Structures Affected: One Apartment Building Height of Bank: 70 ft. (21m) Length of Bank: 80 ft. (24m) Sewell Road at Finch Avenue Rouge River Scarborough 16 Problem: Slope Failure and Riverbank Erosion Structures Affected: Roadway Height of Bank: 40 ft. (12m) Length of Bank: 150 ft. (46m) Gwendolen Park Community Tennis Club West Don River North York 17 Problem: Slope Failure Structures Affected: Tennis Courts Height of Bank: 100 ft. (30m) Length of Bank: 250 ft. (76m) n 1 w 0 POOL OF EROSION PRIORITY SITES WATERSHED BOROUGH TECHNICAL PRIORITY COMMENTS o 1 Lk) I-' Humber River York 18 Problem: Riverbank Erosion (Shale Bank) Structures Affected: Four Residences Height of Bank: 50 -60 ft. (18m) Length of Bank: 400 ft. (122m) 1979 WORK PROGRAME C -32 The following table shows the proposed work programme for 1979, together with the accompanying budget analysis: I T E M ESTIMATED COST SUB- TOTAL ADMINISTRATION: Salaries Material & Equipment Rental Travel Expenses Accumulated Vacation Pay (Labour) STUDIES: Engineering: - 55 Wynford Heights & Vicinity - 99 -107 Wier Crescent & Vicinity - 16 -18 Fernwood Gardens Soil: - 8 -14 Bruce Farm Drive - 31 -35 Rivercove Drive - 100 -104 Gwendolen Cres. MAINTENANCE & RE- VEGETATION PROGRAMME: MINOR REMEDIAL WORK: Kennedy Road Mall Beechgrove Park (Col. Danforth Park) Meadowvale Rd. - Phase I 34 Restwell Crescent Leslie at Sheppard (Dam Wingwall) Zoo (Site Z -15 - Roadway) 92 -94 Celeste Drive - 20 -28 Dunning Crescent Vicinity - 51 Orchard Park Crescent - 2 Barkwin Drive MAJOR REMEDIAL WORK: - 35 Canyon Avenue - 50 -58 Stanwood Crescent - 10 Codeco Court Vicinity - Enfield /Sunset /Jellico Vicinity $ 46,000. 1,200. 1,000. 2,800. 6,000. 12,000. 5,000. 10,000. 3,500. 3,000. 1,500. 22,000. 3,000. 10,000. 10,000. 7,000. 5,000. 6,500. 4,000. 9,500. 4,000. 1,000. 260,000. 128,000. 170,000. 68,000. $ 57,000. 27,000. 8,000. 22,000. 60,000. 626,000. TOTAL $ 800,000. C -33 SCHEDULE "C" TO: THE CHAIRMAN AND MEMBERS OF THE FLOOD CONTROL AND WATER CONSERVATION ADVISORY BOARD, MTRCA - Meeting #3/78 RE: EROSION CONTROL AND BANK STABILIZATION IN THE REGIONS OF PEEL, YORK AND DURHAM - 1979 PROGRAMME Submitted herewith is a staff report outlining the 1979 work programme and the current priorities for the Regions of Peel, York and Durham. RECOMMENDATIONS: IT IS RECOMMENDED THAT: The 1979 Work Programme and the Current Priorities for the Regional Municipalities of Peel, York and Durham be approved. M.R. Garrett Administrator Water Resource Division 1978.08.17 AGS:dms C -34 EROSION CONTROL AND BANK STABILIZATION IN THE REGIONS OF PEEL, YORK & DURHAM - 1979 PROGRAMME Following the erosion inventory and priority studies that have been carried out for the Regions of Peel, York and Durham, a list of proposed remedial work sites has been prepared for each region. It should be noted that for the Regions of York and Durham, the technical priorities identified in the appropriate column of the attached charts follow directly from the priorities identified in the respective reports. In Peel, however, this was not totally possible because of the requirement for "equalized assessment" based on cash flow from the constituent municipalities within the Region. In the latter case, it was therefore necessary to establish priorities within each municipality and then schedule the sites in descending order. Consequently, it was not possible to adhere to relative priorities established on a regional basis. The table below shows the budget allocation by Region for the years 1979 -1981, inclusive. REGION 1979 1980 1981 TOTAL Peel $100,000 $100,000 $100,000 $300,000 York 75,000 75,000 25,000 175,000 Durham 25,000 25,000 25,000 75,000 TOTAL $550,000 Erosion Inventory: The following table indicates the erosion inventory for the primary watercourses within the Regions of Peel, York and Durham. These sites have been identified by design block, where the Authority has either been informed by way of requests for assistance or is aware of a significant erosion problem. C -35 MUNICIPALITY WATERCOURSE NO. OF SITES TOTAL Region of Peel Region of York Region of Durham Etobicoke Creek Mimico Creek Humber River - Main Branch - West Branch Humber River - Main Branch - West Branch - East Branch Don River - West Branch - East Branch - German Mills Creek Rouge River - Main Branch - Little Rouge West Duffin Creek Rouge River - Main Branch Petticoat Creek Duffins Creek- Main Branch - West Branch - East Branch Carruthers Creek 93 11 5 63 93 11 68 TOTAL NO. OF SITES: 172 22 13 37 15 13 9 46 53 7 TOTAL NO. OF SITES: 5 21 26 169 113 42 72 37 99 7 215 5 21 TOTAL NO. OF SITES: 308 42 376 EROSION PRIORITY SITES REGION OF PEEL PROPOSED MAJOR REMEDIAL WORK SITES FOR 1979 -- REGION OF PEEL LOCATION WATERSHED MUNICIPALITY TECHNICAL PRIORITY ESTIMATED COST 1 COMMENTS w EC -18 Ponytrail Drive and Steepbank Crescent Etobicoke Creek Mississauga 1 $ 60,000.00 Problem: Riverbank erosion and slope fail - ure (exposed shale) Structures Affected: 12 Residences Height of bank: 10m Length of bank: 310m EC -58 Mill Street Etobicoke Creek Brampton 2 Phase I 20,000.00 ' (1979) Phase II (1980) Problem: Riverbank erosion and slope failure Structures Affected: 4 Apartment Buildings Height of bank: llm Length of bank: 100m HR -109 North of Albert Street Main Humber Caledon 3 20,000.00 Problem: River bank erosion Structures Affected: 5 Residences Height of bank: 2m Length of bank: 200m 1978.08.15./K POOL OF EROSION PRIORITY SITES -- REGION OF PEEL LOCATION WATERSHED MUNICIPALITY 1 PRIORITY APPROX. COST COMMENTS PROJECTED WORK YEAF EC -58 Mill Street Etobicoke Cr. Brampton 2 $ 5,000.00 Phase II Problem: Riverbank erosion and slope failure Structures Affected: 4 Apartment Buildings Height of bank: llm Length of bank: 100m 1980 EC -16 Neilson Drive Etobicoke Cr. Mississauga 4 18,000.00 • Problem: Riverbank erosion and slope failure Structures Affected: 1 Apartment Building Height of bank: llm Length of bank: 70 - 80m 1980 SIC -96 Derry Road Mimico Creek Mississauga 5 7,500.00 Problem: Riverbank erosion Structures Affected: Storm Sewer Height of bank: 3m Length of bank: 70m 1980 Lot 14, Conc. 5 West Half Main Humber Caledon 6 5,000.00 Problem: Riverbank erosion Structures Affected: Road Height of bank: 3m Length of bank: 15m 1980 4H -140 Wildfield West Humber Brampton 7 5,000.00 Problem: Riverbank erosion Structures Affected: 1 House Height of bank: 3m Length of bank: 60m 1980 1H -141 Wildfield West Humber Brampton 8 15,000.00 Problem: Riverbank erosion and slope failure Structures Affected: 1 Residence Height of bank: 12m Length of bank: 60m 1980 n 1 w co POOL OF EROSION PRIORITY SITES -- REGION OF PEEL (2) LOCATION WATERSHED MUNICIPALITY PRIORITY APPROX. COST COMMENTS PROJECTED WORK YEAR III-142 Wildfield West Humber Brampton 9 $ 3,000.00 Problem: Riverbank erosion and slope failure Structures Affected: 1 Residence Height of bank: llm Length of bank: 60m n 1980 w w 1H -158 East of 6th Line West Humber Brampton 10 2,000.00 • Problem: Riverbank erosion Structures Affected: Proposed residential dvlpmt Height of bank: 12m Length of bank: 50m 1980 :C -8 Applewood Hills Park Etobicoke Creek Mississauga 11 18,000.00 Problem: Riverbank erosion Structures Affected: Parkland Height of bank: 2m Length of bank: 130m 1980 IC -99 Derry Road Mimico Creek Mississauga 12 14,000.00 Problem: Riverbank erosion Structures Affected: 1 Residence Height or bank: 2m Length of bank: 120m 1980 IC -101 Derry Road Mimico Creek Mississauga 13 2,500.00 Problem: Slope failure Structures Affected: 1 Residence Height of bank: 3m Length of bank: 15m 1980 IR -110 Centennial Drive Humber River Caledon 14 5,000.00 Problem: Slope failure (fill material) Structures Affected: 1 Residence Height of bank: 29m Length of bank: 250m IH -159 Humber River Brampton 15 10,000.00 Problem: Riverbank erosion & slope failure POOL OF EROSION PRIORITY SITES -- REGION OF PEEL (3) LOCATION WATERSHED MUNICIPALITY PRIORITY l APPROX. COST COMMENTS WH -172 West of 6th Line Humber River Brampton 16 $ 5,000.00 Problem: River bank erosion and slope failure Structures Affected: Race Track Height of bank: 17m Length of bank: 70m EC -59 Vodden at Highway 7 Etobicoke Creek Brampton 17 8,000.00 Problem: Slope failure (fill material) Structures Affected: Factory work yard Height of bank: 3m Length of bank: 65m WH -161 East of 8th Line Horse Ranch West Humber River Brampton 18 6,000.00 Problem: Slope instability Structures Affected: 1 Residence Height of bank: 21m Length of bank: 70m WH -157 Wildfield West Humber River Brampton 19 6,000.00 Problem: Slope instability and riverbank erosion Structures Affected: Proposed residential development Height of bank: 9m Length of bank: 95m EC -14 Dundas Street Etobicoke Cr. Mississauga 20 . 18,000.00 Problem: Riverbank erosion & slope instability (exposed shale) Structures Affected: 4 Factories Height of bank: 6m Length of bank: 90m EC -15 South of Dundas St. Etobicoke Cr. Mississauga 21 9,000.00 Problem: Riverbank erosion & slope instability (exposed shale) Structures Affected: Factory Parking Lot Height of bank: 9m n Length of bank: 120m 0 contd. POOL OF EROSION PRIORITY SITES -- REGION OF PEEL (4) LOCATION WATERSHED MUNICIPALITY PRIORITY APPROX. COST COMMENTS ' .3C -43 West of Airport Road North of Brittania Etobicoke Creek Mississauga 22 $ 21,000.00 Problem: Riverbank erosion and slope failure Structures Affected: 2 Factories Height of bank: 12m Length of bank: 120m EC -26 South of Highway 401 Etobicoke Cr. Mississauga 23 12,000.00 Problem: Slope failure Structures Affected: 2 Factories Height of bank: 6m Length of bank: 80m 1978.08.15./K EROSION PRIORITY SITES REGION OF YORK PROPOSED MAJOR REMEDIAL WORK SITES FOR 1979 -- REGION OF YORK (1) LOCATION WATERSHED MUNICIPALITY TECHNICAL PRIORITY ESTIMATED COST COMMENTS w Off Kipling - below Highway No. 7 (HMI /P) Humber River Rainbow Creek Vaughan 1 $ 3,250.00 Problem: Riverbank erosion and slope failure. Structures Affected: 1 Residence Height of bank: 17m Length of bank: 70m Lot 19, Conc. III (R2 1 /S) Rouge River Markham 2 6,700.00 • Problem: Riverbank erosion and slope failure Structures Affected: Industrial Building Height of bank: 12m Length of bank: 20m Lot 7, Conc. VIII (R2 /IIN) Rouge River Markham 3 19,400.00 Problem: Riverbank erosion and slope failure Structures Affected: 3 Residences Height of bank: 15m Length of bank: 120m 7440 - Kipling Avenue (H1 I/P & H2 I /P) Humber River Vaughan 4 & 5 15,500.00 Problem: Riverbank erosion and slope failure Structures Affected: 1 Residence Height of bank: 18m Length of bank: 40m 8240 Pine Valley Drive Humber River Vaughan 6 9,200.00 Problem: Slope failure (fill material) Structures Affected: 3 Residences Height of bank: 31m Length of bank: 18m Lot 30, Conc. VIII (LR1 IV /P) Little Rouge Markham 7 8,500.00 Problem: Riverbank erosion Structures Affected: Arterial Road Height of bank: 2m T,....,-,4-1, e.f 1.mnb . 111m PROPOSED MAJOR REMEDIAL WORK SITES FOR 1979 J -- REGION OF YORK(2) LOCATION WATERSHED MUNICIPALITY TECHNICAL PRIORITY ESTIMATED COST COMMENTS Off Kipling below Highway No. 7 (H1 II /P) Humber Vaughan 8 $ 7,300.00 Problem: Riverbank erosion and slope failure Structures Affected: 1 Residence Height of bank: 24m Length of bank: 40m Lot 6, Conc. VIII (R1 IV /P) Rouge Markham 9 2,500.00 Problem: Riverbank erosion Structures Affected: Arterial Road Height of bank: 10m Length of bank: 45.7m Lot 10, Conc. VII (H4 I /P) Humber Vaughan 10 Phase I 2,000.00 (1979) Phase II (1980) Problem: Riverbank erosion and slope failure Structures Affected: 2 Residences Height of bank: 24m Length of bank: 100m 1978.08.15./K c1 1 POOL OF EROSION PRIORITY SITES -- REGION OF YORK LOCATION WATERSHED MUNICIPALITY TECHNICAL PRIORITY APPROX. COST COMMENTS PROJECTED WORK YEAR Lot 10, Conc. VII (H4 I /p) Humber Vaughan - 10 $ 2,700.00 Phase II Problem: Riverbank erosion and slope failure Structures Affected: 2 Residences Height of bank: 24m Length of bank: 100m n 1980 "' Lot 11, Conc. III (D2 I /S) West Don Vaughan 11 1,800.00 Problem: Riverbank erosion Structures Affected: 1 Industrial Building Height of bank: 4m Length of bank: 30m 1980 Lot 30, Conc. I (ED3 IV /P) East Don Markahm 12 3,500.00 Problem: Gully erosion Structures Affected: Railroad Height of bank: 10m Length of bank: 15m 1980 Between Clarence St. and Islington Avenue (H2 IV /P) Humber Vaughan 13 4,300.00 Problem: Riverbank erosion Structures Affected: Road Height of bank: 5m Length of bank: 45m 1980 Lot 8, Conc. VIII (H4 II /P) Humber Vaughan 14 8,000.00 Problem: Riverbank erosion and slope failure Structures Affected: 1 Residence Height of bank: 18m Length of bank: 65m 1980 Lot 36, Conc. 1 (ED1 II /S) East Don West Vaughan 15 2,500.00 Problem: Riverbank erosion Structures Affected: 1 Road Height of bank: 4m Length of bank: 80m 1980 POOL OF EROSION PRIORITY SITES -- REGION OF YORK (2) LOCATION WATERSHED MUNICIPALITY TECHNICAL PRIORITY APPROX. COST COMMENTS PROJECTEC WORK YEAF East of Islington Avenue, South of Pinegrove (H3 IV /P) Humber Vaughan 16 $ 1,700.00 Problem: River bank erosion Structures Affected: Storm sewer outlet Height of bank: 5m Length of bank: 35m 1980 Lot 3, Conc. VIII (R1 I /P) Rouge Markham 17 750.00 - Problem: River bank erosion and slope failure Structures Affected: 1 Residence Height of bank: 6m Length of bank: 40m 1980 Highway 27 & King /Vaughan Road (H3 II /S) Humber Vaughan 18 16,000.00 Problem: Riverbank erosion and slope failure Structures Affected: 1 Residence Height of bank: 5m Length of bank: 180m 1980 Lot 15, Conc. VII (H5 II /S) Humber Vaughan 19 1,000.00 Problem: Riverbank erosion Structures Affected: Road Height of bank: 2m Length of bank: 50m 1980 Lot 3, Conc. VIII (R3 III /D) Rouge Markham 20 10,500.00 Problem: Riverbank erosion and slope failure Structures Affected: Golf Course Height of bank: 9.2m Length of bank: 61.Om 1980 Lot 8, Conc. VIII (R5 III /D) Rouge Markham 21 10,500.00 Problem: Riverbank erosion and slope failure Structures Affected: Golf Course Height of bank: 9m Length of bank: 61m /contd. 1980 0 1 m POOL OF EROSION PRIORITY SITES -- REGION OF YORK (3) LOCATION WATERSHED MUNICIPALITY TECHNICAL APPROX. COMMENTS PROJECTED EAR Lot 9, Conc. VII (H2 II /P) Humber Vaughan 22 $ 4,700.00 Problem: Slope failure Structures Affected: 4 Residences Height of bank: 18m Length of bank: 107m n 0. 1980 "' Pine Grove Road (H32 III /D) Humber Vaughan 23 1,800.00 Problem: River bank Structures Affected: 1 Residence Height of bank: 3m Length of bank: 40m 1980 Glenbourne Park Rouge Markham 24 2,500.00 Problem: Riverbank erosion Structures Affected: 1 Residence Height of bank: 2m Length of bank: 40m 1980 L978.08.15./K EROSION PRIORITY SITES REGION OF DURHAM PROPOSED MAJOR REMEDIAL WORK SITES FOR 1979 -- REGION OF DURHAM LOCATION WATERSHED MUNICIPALITY TECHNICAL PRIORITY ESTIMATED COST COMMENTS QD D -19 Phase I River bank and slope failure. Whitevale Golf Course Rouge Pickering 1 $25,000.00 (1979) Structures Affected: Golf Course Height of bank: 75 feet (23m) Phase II Length of bank: 580 feet (180m) (1980) L978.08.15./K POOL OF EROSION PRIORITY SITES -_ REGION OF DURHAM LOCATION WATERSHED MUNICIPALITY TECHNICAL PRIORITY APPROX. COST COMMENTS PROJECTEC WORK YEAI D -19 Whitevale Golf Course Rouge Pickering 1 Phase II $ 6,000.00 Problem: River bank and slope failure 1980 D -24 Hockey Ranch Duffin Pickering 2 3,500.00 Problem: River bank and slope failure Structures Affected: 1 Swimming Pool Height of bank: 30 feet (9.Om) Length of bank: 30 feet (9.Om) 1980 558 Pine Ridge Road Rouge Pickering 3 5,000.00 Problem: River bank and slope failure Structures Affected: 1 Pool and 1 Residence Height of bank: 20 feet (6.Om) Length of bank: 20 feet (6.Om) 1980 D -25 Elizabeth Street Duffin Pickering 4 7,300.00 Problem: River bank and slope failure Structures Affected: 1 Residence Height of bank: 5 feet (1.5m) Length of bank: 160 feet (50m) 1980 D -17 Whitevale Golf Course Rouge Pickering 5 3,200.00 Problem: River bank and slope failure Structures Affected: Utility Shed (Pump House) Height of bank: 10 feet (3.Om) Length of bank: 150 feet (45m) 1980 1978.08.15./K 0 1 u, 0 POOL OF EROSION PRIORITY SITES -- REGION OF DURHAM LOCATION WATERSHED MUNICIPALITY EC HNI L TECHNICAL EC NI APPROX. COST COMMENTS �;, H D -21 Near Clarke's Hollow Duffin Creek Pickering 6 $ 7,000.00 Problem: River bank and slope failure Structures Affected: 1 Residence Height of bank: 130 feet (40m) Length of bank: 420 feet (130m) D -23 Greenwood Road Lot 12, Conc. V Duffin Creek Pickering 7 9,000.00 Problem: River bank and slope failure Structures Affected: 1 Swimming Pool Height of bank: 60 feet (18m) Length of bank: 140 feet (42.5m) D -16 Brock Road Duffin Creek Pickering 8 9,000.00 Problem: Slope failure and river bank erosion. Structures Affected: Dining Pavilion + Recreation Area Height of bank: 15 feet (4.5m) Length of bank: 540 feet (165m) 1978.08.15./K C -52 1979 Work Programme The following table shows the proposed work programme for 1979 and the accompanying budget analysis for each of the Regions of Peel, York and Durham. REGION ITEM ESTIMATED COST SUB -TOTAL Peel Administration Remedial Work Sites North of Albert Street Bolton Mill Street - Brampton Ponytrail Drive Mississauga $ 6,500.00 18,700.00 18,700.00 56,100.00 $ 6,500.00 93,500.00 TOTAL $100,000.00 York Administration Remedial Work Sites 7476 Kipling - Vaughan Lot 19, Conc III Markham Lot 7, Conc VIII Markham 7440 Kipling - Vaughan 8240 Pine Valley Drive Vaughan Lot 30, Conc VIII Markham Off Kipling below Highway 7 Vaughan Lot 6, Conc VIII Markham Lot 10, Conc VII Vaughan 4,900.00 3,000.00 6,300.00 18,200.00 14,500.00 8,600.00 8,000.00 6,800.00 2,300.00 2,400.00 4,900.00 70,100.00 TOTAL $ 75,000.00 Durham Administration Remedial Work Sites Whitevale Golf Course 7th Green, Pickering 1,600.00 23,400.00 1,600.00 23,400.00 TOTAL $ 25,000.00